Ramp B-D (Exit 2)

08072020 #5.jpg

Project Details

Location:
North Hampton
New Hampshire
Client:
New England Infrastructure
General Contractor:
New England Infrastructure
Completion Date:
June, 2023
Deck Width (FT.):
31
Bridge Deck Area (SQ. FT.):

8,205

Deck Rebar (LBs):

60,647

Total Ties:

5,369

Tie Requirements:
0
% Bottom /
50
% Top
IronBOT LBs Placed

N/A