Client Projects

Project & Crew Information:
- General Contractor: Brayman
- Rebar Contractor: N/A (Self-Perform)
- Union: Laborers Local 1058
- Crew Size: 10-person
- Shift Duration: 10-hour
- Products Used: TyBOT
- March 2019 β April 2019
β
TyBOT Performance Metrics:
- Actual Ties: 111,645 (89% Total)
- Active Production Hours: 99
- Active Tie Rate: 1,128 Ties/HR
- Total Equipment Hours: 120
- Active Production Rate = 83%
- Equipment Utilization Rate = 92%
β
ACR Project Scope:
- 2 of 4-Span Bridge Deck
- Bridge Deck SF: 26,445
- Width:43β
- Length:6 15β
- Horizontal Deck Rebar: 269,000LBS
- Total Deck Intersections: 125,250
- Tie Specs: 50% Bottom / 100% Top
β
β

β